项目名称:
Gas detector pipe modification for M/V CMA CGM CONCORDE
项目开始时间:
2024-05-17 16:32
项目类型:
othere
项目描述:
According to the ship information provided by the owner,the gas detector pipe need modification , so a total of four people from the SEASAVE service team were at the port of shanghai on 29th,Apr 2024 to carry out the hot work.
进展:
Check, put up fire cloth and cut holes




进展:
Make and weld new heavy plate




进展:
Install pipe fittings and pipe layout








进展:
Job done