项目描述:
According to the ship information provided by the owner,EGR cooler leaks need to repair the leaking area, As a result, the SEASAVE service team conducted dismantling and repair operations on 14 May 2024 at the Nansha Port.
进展:
Check and dismantle air cooler cover.




进展:
Identify the leak area and blockages.


进展:
Reinstall cooler and pressure water test.
Apply glue and replace the new seal ring,reinstall the air cooler valve,Bolts and connecting all accessory,test for leakage.
After the installation, the pressure water test was performed and no leakage was found.



进展:
Job done

项目名称:
EGR cooler repaired for M/V MAERSK CINCINNATI
项目开始时间:
2024-05-17 15:05
面积:
装修风格:
othere
装修单元类型:
According to the ship information provided by the owner,EGR cooler leaks need to repair the leaking area, As a result, the SEASAVE service team conducted dismantling and repair operations on 14 May 2024 at the Nansha Port.
区域:
进展:
Check and dismantle air cooler cover.




进展:
Identify the leak area and blockages.


进展:
Reinstall cooler and pressure water test.
Apply glue and replace the new seal ring,reinstall the air cooler valve,Bolts and connecting all accessory,test for leakage.
After the installation, the pressure water test was performed and no leakage was found.



进展:
Job done